ARCOTEC_Mormon_Temple2-1

Project Description

Client:   Westland Construction | The Church of Jesus Christ of Latter-day Saints
Location:   Route de Frères, Pétion-ville
Surface Area: 5,000 m2
Year Completed:   2019
Architect:   CRSA Architects
Scope of Works: Subcontractor | Site Clearing & Preparation | Backfill & Compaction | Partial Demolition | Reinforced Concrete & Masonry | Specialty Concrete | Architectural Precast Concrete | Curbs & Sidewalks | Trenching and Drainage | Stucco Work

The Challenges

Completed in 2019, the first Temple in Haiti of The Church of Jesus Christ of Latter-day Saints. Under the supervision of Westland Construction Management Company, Arcotec was the project’s primary subcontractor.

Our construction company carried out the earthwork and civil work required to prepare the site for construction. In addition, we excavated to the proper depth for the foundation. We were also responsible for creating the concrete shell for the building and also executed masonry and stucco work.